Metrolinx is Ordered to Reveal Documents Showing Anticipated Timelines for Making the Mimico Go Station Accessible to Passengers with Disabilities
November 27, 2026
SUMMARY
Here’s yet another illustration of serious problems with how the Ford Government’s Metrolinx agency deals with its responsibility to tear down disability barriers in the public transit facilities it operates or builds. Metrolinx is responsible for the Go Transit public transit system in Ontario. That system is far from barrier-free despite the Accessibility for Ontarians with Disabilities Act’s requirement for Ontario (including public transit) to be accessible by the start of 2025.
The Mimico Go Transit station is entirely inaccessible to passengers with mobility disabilities. This is not news. The Mimico Residents’ Association has been pressing for years to get this problem fixed. Among other things, it has tried to get Metrolinx to let the public know when that station will be retrofitted so that it will be accessible. Those residents have not been able to get an answer.
We applaud a Mimico resident for filing a Freedom of Information application to try to unearth Metrolinx’s plans. Metrolinx refused to produce those plans for bogus reasons. The Mimico resident appealed that refusal to Ontario’s Information and Privacy Commission. A very good November 24, 2026 Toronto Star article reports that the Mimico resident won its appeal. Metrolinx has been ordered to reveal the internal anticipated timetable for making this station accessible. We set out that article below, as well as a November 24, 2026 article from the railway industry’s Railway Supply publication. CBC TV Toronto’s November 24, 2026 edition included a great report on this issue. The June 16, 2026 AODA Alliance Update also described the Mimico Residents’ Association’s multi-year efforts to get answers from Metrolinx.
It is utterly appalling that Metrolinx refused to disclose the requested information and that it advanced obviously meritless legal arguments to justify its refusal. The Information and Privacy Commission properly saw through those hollow excuses. It is also repugnant that Metrolinx wasted public money fighting against disclosure of this information. As a provincial government agency, it should be open and transparent about its plans to address accessibility, not secretive. It should not burden a member of the public with the hardship of fighting a Freedom of Information application appeal.
The November 24, 2026 CBC TV news report on this issue stated that Metrolinx did not directly answer whether it would try to appeal the decision of the Information and privacy Commission. It would be a serious misuse of public funds for Metrolinx to drag out this issue any further by trying to take this to court.
The Mimico Go Transit station is most certainly not the only instance of Metrolinx falling down on accessibility for passengers with disabilities. Earlier this year, the AODA Alliance released online videos revealing accessibility bungles on Toronto’s new Eglinton Crosstown transit line and on Toronto’s new Finch West transit line. Metrolinx designed and built both of those lines.
How You Can Help
- If you live in a neighbourhood with a residents’ association, urge it to advocate for fixing disability barriers in your area. Offer to work with them on this advocacy. Tell them that everyone is bound to eventually have a disability.
- To get your residents’ association started, encourage them to listen to Disability Rights and Wrongs — The David Lepodcast to get advocacy action tips. For more on our podcast, visit the AODA Alliance website’s new podcast page. Also encourage them to check out our new video series giving practical tips for social justice advocacy.
- Write Premier Ford at premier@ontario.c.a and your local member of the Ontario Legislature. You can find your MPP’s contact information on the Ontario Legislature’s web page. Tell them Metrolinx is doing a terrible job at ensuring accessibility on public transit for riders with disabilities.
- Share this news report with others.
- Tell your local media about disability barriers you encounter at public transit stations, including those for which Metrolinx is responsible.
- Write Metrolinx at accessibility@metrolinx.com to alert them to any disability barriers you have experienced or seen at a transit station or stop for which Metrolinx is responsible.
- If you haven’t yet watched them, check out our 5-minute video on the stupidest ramp in the world as well as our earlier video on wayfinding accessibility blunders on the Eglinton Crosstown transit line. Share them with others.
- We’ve advocated for accessible transit for years. Watch the May 2018 AODA Alliance online video about disability blunders in new and renovated Toronto-area transit stations. Visit the AODA Alliance website’s public transportation page.
- We know that a number of our AODA Alliance Updates sadly must focus on problems and roadblocks in the campaign for accessibility. Never be discouraged! There is also important good news. You can find a very encouraging number of stories along with advocacy action tips by listening to our podcast that comes out with a new episode every third Friday. It is called Disability Rights and Wrongs — The David Lepodcast. Learn more about it on the AODA Alliance website’s podcast page.
MORE DETAILS
Toronto Star November 24, 2026
Ontario watchdog orders Metrolinx to reveal internal records on long-delayed Mimico GO station upgrades
Metrolinx said accessibility improvements at the station are a priority. The construction contract is expected to be awarded in 2027.
Accessibility upgrades were initially planned for completion by 2016. Construction work has yet to begin.
By Sheila Wang Investigative Reporter
Ontario’s transparency watchdog has ordered Metrolinx to release project schedule details for a GO station accessibility upgrade that was supposed to be finished a decade ago.
The provincial transit agency had planned to make the Mimico GO Station on the Lakeshore West Line barrier-free by 2016, but to date no construction work has been done.
Through freedom-of-information legislation, a local resident asked for a document that spells out the agency’s project timelines, but it was sent with heavy redactions.
The decision, issued on Nov. 12, comes as Metrolinx faces criticism for a lack of transparency into significant delays and cost overruns on multiple infrastructure projects. For the Ontario Line and other delayed projects, Metrolinx has refused to release specific opening dates.
Why the Metrolinx file was redacted
In the case of Mimico GO, after a resident requested the information in January 2025, Metrolinx said the redactions to the scheduling record were necessary, in part, to protect the agency’s economic interest.
But the Information and Privacy Commissioner (IPC) decision said Metrolinx failed to provide sufficient evidence to show that the release of the information could cause financial harm, and ordered it to disclose the responsive records.
“Metrolinx’s submissions on harm are highly speculative and do not satisfy the threshold to establish the harms it alleges,” Steven Faughnan, an adjudicator at the IPC, wrote in the decision.
David Lepofsky, chair of the Accessibility for Ontarians with Disabilities Act (AODA) Alliance, applauded the decision but said he was concerned that Metrolinx staff, paid by the public purse, are trying to “block public accountability.”
“They are not telling the public anything who has a right to know. At the same time they’re covering up their internal plans and they are foot dragging, and putting a member of the public to the ridiculous burden of having to fight and appeal to the Information and Privacy Commissioner to win,” Lepofsky said.
Metrolinx faced criticism after it recently announced that it will reduce the number of its board meetings, when staff often provide project updates, from four times a year to two, the CBC reported.
In response to questions from the Star, Metrolinx did not address the commissioner’s ruling or the transparency concerns, stating that its priority “is improving accessibility at Mimico station and providing customers with a seamless, integrated and barrier-free experience.”
Why is Mimico GO still not accessible?
Built in 1967, Mimico GO has long been identified by Metrolinx as a station that needs to be rehabilitated to meet its standards for accessibility.
The initial 2016 completion deadline for an accessibility upgrade was pushed to 2017.
At Mimico GO station, long due for an upgrade, passengers must use the stairs and existing underground tunnels to reach the platforms.
Then the project suffered multiple additional delays and alterations over the next decade, with the completion date pushed to 2023, then to 2025. Metrolinx won’t disclose its current targeted completion date. Over the years, the original design has changed from a new pedestrian bridge over the tracks, to new underground tunnels with elevators, and then back to a pedestrian bridge.
The upgrade had also been considered as part of a broader effort by the provincial government to develop the area as a Transit-Oriented Community (TOC), though that plan was abandoned.
The station work has still not broken ground. Passengers must use the old stairs in the existing underground tunnels to reach the platforms.
Living with an inaccessible station
“Someone really has to be there (at the station) to assist me … and someone has to carry my walker,” said Katelyn Eathorne, who uses a rollator walker — a four-wheeled mobility aid — after she suffered a stroke six years ago.
Without automatic doors, elevators and ramped platforms for level boarding at the Mimico station, it’s impossible for her to use the GO Line on her own, she said.
As part of Metrolinx’s most recent plan, Mimico GO’s upgrades will include a pedestrian bridge with elevator and a new building entrance, according to the agency.
Eathorne said that between the grand promises touted in public meetings and the quietly missed deadlines, Metrolinx has not kept the public well informed about what is actually happening.
During mediation of the dispute over access to the project timeline, Metrolinx handed over a version of the document that revealed some information, which was obtained by the Star and offers a glimpse into what has been happening behind the scenes.
It took half a year for Metrolinx to procure design services for the station upgrades and nearly another year to hire a construction manager.
Metrolinx told the Star that a contract for design and construction management services was awarded in May 2025, and the contract for major construction is expected to be awarded in 2027.
Metrolinx argued to the IPC that a fully-disclosed record could be “misconstrued or lead to further confusion and frustration by the public,” noting that several separate issues at Mimico GO have been conflated within the media, leading to “negative public sentiment.”
The adjudicator ruled that FOI exemptions are not meant to “insulate institutions” from public disappointment.
Metrolinx is required to release the record by Dec. 21, almost two years after the agency first received the public-record request.
“Justice delayed is justice denied,” said Duff Conacher, co-founder of Democracy Watch. “This is a victory at the end, but two years later than it should have happened. You can take that as encouraging that they finally won, or discouraging that the government was legally able to delay disclosure by two years.”
The transit agency did not say whether it will appeal the IPC decision.
Sheila Wang
Sheila Wang is an investigative reporter for the Star. Reach her via email: sheilawang@thestar.ca
Railway Supply November 24, 2026
Originally posted at https://www.railway.supply/metrolinx-must-release-mimico-go-schedule-for-delayed-step-free-upgrade/
Metrolinx must release Mimico GO schedule for delayed step-free upgrade
By Oleksandr Batrak
CANADA: Ontario’s Information and Privacy Commissioner has ordered Metrolinx to release redacted schedule records for the long-delayed accessibility upgrade at Mimico GO Station, which still lacks step-free access.
The order, issued on Nov. 12 by Steven Faughnan, an adjudicator at the Information and Privacy Commissioner of Ontario (IPC), gives Metrolinx until Dec. 21 to disclose the record, the Toronto Star reported. A local resident requested the document, which sets out the agency’s project timelines, under Ontario’s freedom-of-information law in January 2025 and received a heavily redacted copy.
Metrolinx, the provincial transit agency that runs GO Transit, argued that the redactions were needed partly to protect its economic interests. The adjudicator found that the agency had not provided enough evidence that disclosure could cause financial harm and ordered the responsive records released. In the decision, Faughnan wrote:
“Metrolinx’s submissions on harm are highly speculative and do not satisfy the threshold to establish the harms it alleges.”
Metrolinx also told the IPC that a fully disclosed record could be misconstrued or add to public frustration, arguing that separate issues at the station had been conflated in media coverage. The adjudicator ruled that freedom-of-information exemptions are not meant to shield institutions from public disappointment. Metrolinx did not say whether it will appeal. In a statement to the Star, it said its priority is improving accessibility at Mimico station.
How the Mimico GO completion date kept moving
Mimico GO Station, on the Lakeshore West line in south Etobicoke, was built in 1967, the year GO Transit launched. In its 2013 accessibility status report, Metrolinx said detailed design had begun on a new tunnel with elevators, and that the first tunnel would be built by March 2016 to provide accessible train service from Mimico.
That date did not hold. The Metrolinx 2018–2019 Multi-Year Accessibility Plan said planned improvements would bring the station up to current accessibility standards by the end of 2023. At its June 2024 accessibility consultation, the agency listed the expected completion for Mimico as “schedule currently in development.” Metrolinx has not disclosed a current completion target.
The design has also changed. The Star reported that plans moved from a pedestrian bridge over the tracks to underground tunnels with elevators and then back to a bridge. For several years the rebuild was also linked to a transit-oriented community: in April 2022 Metrolinx signed a binding agreement with Vandyk Properties for a new station alongside a mixed-use development, a plan that was later abandoned. The station work has not broken ground, the Star reported, and passengers still reach the platforms by stairs through the existing underground tunnels.
Rendering of a glass station entrance with MIMICO signage, GO logo, bike racks and pedestrians including a wheelchair user
Rendering of a new street-level entrance building at Mimico GO Station. Image: Metrolinx
What Metrolinx plans to build at Mimico GO
The upgrade described on the Metrolinx project page for Mimico GO Station includes a new east connection with elevator and stair access to the platforms, a new south tunnel entrance at Manchester Street and Blue Goose Street with elevator and stair connections, and tactile walking surface indicators at the platform edge. The Metrolinx 2024 accessibility status report also lists a mini-platform for step-free boarding.
The work is being procured under a construction manager at risk (CMAR) model. The Metrolinx capital projects procurement pipeline lists the Mimico GO Station Tunnel and Platform Rehabilitation in the estimated value class of $90 million to $500 million, with a scope of a new tunnel, a new south station building and rehabilitation of the existing platforms. Prequalification closed in February 2024, proposals closed in March 2025, and the contract was awarded in May 2025.
Metrolinx says a development phase is under way, with a construction manager overseeing design details. On the GO Transit accessibility page for Mimico GO, the agency says that once design is complete, the contractor will provide a construction schedule and cost estimate, and a construction contract would follow if Metrolinx accepts them. Metrolinx told the Star that the major construction contract is expected to be awarded in 2027. The partly released timeline record, which the Star obtained, shows that procuring design services took about six months and hiring a construction manager nearly another year.
Where Mimico stands among GO stations without step-free access
At the June 2024 consultation, Metrolinx said 65 of 68 GO stations were accessible. Its 2024 status report, summarizing that year’s annual public meeting, listed Eglinton, Long Branch and Mimico as the GO stations that did not have a step-free path at the time. Eglinton GO reopened in fall 2024 after its upgrades. By the agency’s May 2026 accessibility public meeting, Long Branch GO was under construction, while Mimico remained in design.
GO stations without a step-free path in 2024: target and status
Station Target in 2018–2019 plan Status in Metrolinx reports
Eglinton GO Late 2022 Upgrades completed in 2024, reopened in fall 2024
Long Branch GO Mid-2023 or sooner Under construction as of May 2026
Mimico GO End of 2023 Design underway as of May 2026; no construction schedule published
Of the three GO stations Metrolinx listed without a step-free path in 2024, Mimico is the only one still in design. Targets come from the Metrolinx 2018–2019 Multi-Year Accessibility Plan; status comes from the Metrolinx 2024 accessibility status report and the May 2026 accessibility public meeting. The plan said scope and timelines could change as GO Expansion evolved.
Until the work is finished, GO Transit directs riders who need step-free access to Union Station or Port Credit GO, with TTC Wheel-Trans and MiWay connections for eligible customers. Katelyn Eathorne, who has used a rollator walker since a stroke six years ago, told the Star that without elevators, automatic doors and level boarding she cannot use the station on her own:
“Someone really has to be there (at the station) to assist me … and someone has to carry my walker.”
David Lepofsky, chair of the Accessibility for Ontarians with Disabilities Act (AODA) Alliance, welcomed the decision but said he was concerned that Metrolinx staff were trying to block public accountability. Duff Conacher, co-founder of Democracy Watch, called the ruling a victory that came two years later than it should have.
AODA Alliance